(Suria KLCC) Fit Out Guidelines - Mall Requirements for Hoarding, Visual & Reinstatement
DISCLAIMER: Please note that these guidelines may change without prior notice; we will do our best to update the information as frequently as possible. The information below is intended for your reference only.
For the most accurate and detailed information, please contact the mall's fit-out team directly.
HOARDING & VISUAL (Indoor Lot & Kiosk) REQUIREMENTS
|
1. |
Hoarding Material |
MDF |
NOTES: Marine Plywood (Proposed Material If Outdoor Hoarding - Expose to Weather) |
|
2. |
Hoarding Structure |
Timber |
|
|
3. |
Hoarding Door Type |
Sliding Door |
1500mm x 2100mm |
|
4. |
Add-On (Counterweight) |
a. For Kiosk (Free-Stand) |
|
|
5. |
Add-On (Fabric) |
Top Fabric Surface Cover |
For Lot & Kiosk |
|
6. |
Hoarding (Kiosk) Height |
Phase 1: |
Clarification:
Then when your team want to start building the kiosk structure, then only can replace top surface fabric with VERTICAL FABRIC. |
|
6. |
Hoarding Visual Material |
Sticker Only |
By Mall Panel Only |
|
7. |
Skirting |
2inch (Bottom Only) |
|
NOTES: Click HERE for sample hoarding and/or visual installation at Suria KLCC for your reference
MALL FIT OUT GUIDELINES
|
1. |
Safety Pledge |
Valid for 3 months NOTES: Compulsory for all site personnel & workers to attend safety briefing at security office to obtain safety pledge before start work on-site. Set appointment prior before attending the safety briefing. |
|
2. |
Site Dilapidation Picture(s) |
Make sure take pictures of existing site condition before start work to avoid any dispute later. |
|
3. |
Floor Protection On-Site |
Compulsory installation of floor protection at common walkway area for trolleys & workers mobilization during on-site work and clear off & clean up on daily basis after daily job done. |
|
4. |
CIDB Green Card |
Worker(s) compulsory to have CIDB Green Card in order to work within the mall. |
|
|
For on-site worker(s) to access WORK AT HEIGHT, it is compulsory under mall safety requirement to use ALUMINIUM SCAFFOLD with GREEN TAG tagging which inspect by AUTHORIZED & COMPETENT SCAFFOLD INSPECTOR. |
REINSTATEMENT GUIDELINES
|
1. |
Preliminaries |
Site Arrangement & Documents Preparation |
|
2. |
Insurance |
RM2mil Public Liability |
|
3. |
Reinstatement |
Dismantle, Demolish, Move Out, Clear Off |
|
4. |
Engage by Contractor(s), To Clear Out from Mall Loading Bay Area before 6am Daily (STRICTLY NO OVERNIGHT) |
|
|
5. |
3rd Party Panel Contractor(s) |
a. Sprinkler |
|
6. |
Touch Up and/or Restoration |
After Site Inspection by Mall Fit Out Team (IF REQUIRED ONLY based on Lot Condition)Frequent Restoration Item(s) as Listed Below: |