(Sunway Putra Mall) Fit Out Guidelines - Mall Requirements for Hoarding, Visual & Reinstatement
DISCLAIMER: Please note that these guidelines may change without prior notice; we will do our best to update the information as frequently as possible. The information below is intended for your reference only.
For the most accurate and detailed information, please contact the mall's fit-out team directly.
HOARDING & VISUAL (Indoor Lot & Kiosk) REQUIREMENTS
|
1. |
Hoarding Material |
MDF |
NOTES: White PVC Plywood or Marine Plywood with Timber Structure Hoarding (Proposed Material If Outdoor Hoarding - Expose to Weather) |
|
2. |
Hoarding Structure |
Timber |
|
|
3. |
Hoarding Door Type |
a. Sliding Door (Lot) |
a. 1220mm x 2440mm |
|
4. |
Add-On (Counterweight) |
a. For Kiosk (Free-Stand) |
|
|
5. |
Add-On (Fabric) |
Not Required |
|
|
6. |
Add-On (Transparent Plastic Sheet) |
Vertical Transparent Plastic Sheet (Kiosk) |
REMARKS: To avoid blocking mall patrons view which having see through effect when a center kiosk at common area installed with a hoarding |
|
7. |
Hoarding (Kiosk) Height |
1220mm (4ft) |
|
|
8. |
Hoarding Visual Material |
Tarpaulin |
|
|
9. |
Skirting |
Aluminium Skirting (1inch) |
Bottom Only |
NOTES: Click HERE for sample hoarding and/or visual installation at Sunway Putra Mall for your reference
MALL FIT OUT GUIDELINES
|
1. |
Pre-Reinstatement Briefing |
Compulsory for a contractor's representative to attend pre-project briefing with mall fit out team to understand the mall and job requirement process flow before start work on-site. |
|
2. |
Site Dilapidation Picture(s) |
Make sure take pictures of existing site condition before start work to avoid any dispute later. |
|
3. |
Floor Protection On-Site (Canvas OR FloorGard) |
Compulsory installation of floor protection at common walkway area for trolleys & workers mobilization during on-site work and clear off & clean up on daily basis after daily job done. |
|
4. |
CIDB Green Card |
Worker(s) compulsory to have CIDB Green Card in order to work within the mall. |
|
5. |
a. OSH-Coordinator (OSH-C) |
Each project is compulsory to have either one of the role stated depends on project value to base on-site in order to comply to the safety requirement set by mall management. |
|
|
Aluminium Scaffold (BS SCAFFOLD) |
For on-site worker(s) to access WORK AT HEIGHT, it is OPTIONAL under mall safety requirement to use ALUMINIUM SCAFFOLD with GREEN TAG tagging which inspect by AUTHORIZED & COMPETENT SCAFFOLD INSPECTOR. |
REINSTATEMENT GUIDELINES
|
1. |
Preliminaries |
a. Site Arrangement |
|
2. |
Insurance |
a. RM1mil Public Liability |
|
3. |
Reinstatement |
a. Dismantle |
|
4. |
a. Engage by Mall Management |
|
|
5. |
3rd Party Panel Contractor(s) |
a. Sprinkler |
|
6. |
Touch Up and/or Restoration |
After Site Inspection by Mall Fit Out Team (IF REQUIRED ONLY based on Lot Condition) |