PHASE 1 (ON-SITE ARRANGEMENT)
No. | Job Step | Description |
1 | Lorry & workers reach onsite |
|
2 | Unload all materials and equipment from lorry |
|
3 | Barricade temporary storage area onsite |
|
4 | Barricade work area and floor protection on common walkway area (if require) |
|
PHASE 2 (WORK IN PROGRESS)
No. | Job Step | Description |
5 | Prepare ladder for working at height |
|
6 | Erect scaffold (if require) |
|
7 | Hoarding marking after on-site measurement checking |
|
8 | Hoarding with OR without concrete counterweight installation(Building Façade Hoarding) |
|
9 | Hoarding with scaffold structure installation (Building Façade Hoarding with Scaffold Structure, hoarding height exceed 8 meters) |
|
10 | Hoarding tarpaulin visual installation |
|
PHASE 3 (WORK INSTALLATION COMPLETE)
No | Job Step | Description |
11 | Testing |
|
12 | Packing up |
|
13 | Clean up |
|
14 | Snap pictures for reporting |
|